Andrew Musgrave
Welcome again to ASX Briefs, and today I'm joined by Andrew King, the CEO of VHM Limited. VHM is currently developing a rare earths and mineral sands project in Victoria. Andrew, great to have you with me today and welcome to the ASX Briefs Podcast.
Andrew King
Andrew, thank you very much for having me and giving me the opportunity to talk to you.
Andrew Musgrave
Okay, and now for listeners that may be unfamiliar with the company, can you just provide a brief overview, please?
Andrew King
Certainly. VHM is a rare earth and mineral sands developer. We're based in Melbourne, and we own 100% of the Goschen project based up in Northwest Victoria in the Mallee region. The Goschen Project is a shallow sand deposit that produces two key products. Firstly, a rare earth concentrate, and secondly, a heavy mineral concentrate of zircon and titanium. Most interestingly, in that is that the rare earth concentrate contains both light and heavy rare earths, which in the current world scenario is very important. And the heavy rare earths include dysprosium and terbium, which are particularly sensitive in the global market at the moment. The project itself is fully permitted, and we have binding agreements with Iluka for 100% of the rare earth concentrate for the full life of the mine, and a non-binding agreement with Mitsui for 50% of our HMC, that's the zircon titania concentrate, for up to 65,000 tons. For the company, as part of that agreement with Iluka, there is included a $40 million cornerstone investment in the building of the Goschen project. And with the non-binding agreement we have with Mitsui, we're working towards working with Mitsui towards that expanding to include 100% of the heavy mineral concentrate, and discussing Mitsui themselves, providing some funding with the provision of a working capital facility. The project has recently refreshed its DFS, a definitive feasibility study, showing very strong economics. And really, all we're left to do as we're fully permitted is now complete the financing, take it through to FID, final investment decision with the board, and we can commence construction with all those things in place.
Andrew Musgrave
Now looking at the DFS, which confirms a pre-tax NPV of 807 million Aussie dollars, an IRR of 33%, and a three-year payback from commencement of production. Can you walk us through what's driving those strong returns and how the refreshed numbers compare to the original study?
Andrew King
Yes, it is very strong economics, and thank you for the question. The key drivers are for the Goschen project, it's a very simple mining and processing project. The mining is all sand. So, Mother Nature has done a lot of the work. It's very low energy, there's no crushing required or blasting, and it's all above the water table. So, from a mining perspective, it's a very simple process and very low cost. Secondly, we have two revenue streams that sell into unrelated markets. So, if we use the heavy mineral concentrate as a credit, it means that as a mining project is a rare earth project, it will be a very low-cost rare earth mining operation. With the Iluka pricing, and that is the third driver for the DFS, is we have an agreement with Iluka that looks right through to the market, and the pricing we receive with for our product is what the end pricing will be, utilizing West the Western pricing model and the forecast for rare earths going forward. So, we have a direct exposure through our off take with Iluka to that pricing.
Andrew Musgrave
And execution capital has been set at Aussie dollars 283 million with total funding required of 482 million based on refreshed tenders and vendor quotations. How confident are you in these market tested numbers?
Andrew King
Andrew, look, we're very confident in those numbers. We have gone to market with all the packages in a competitive tender process and updated those to the latest costs that needed to be inputted. We've included a contingency of about $24 million. There were some movements in those input costs from previous work, and I probably didn't answer that properly in your last question. But those input costs have remained reasonably steady throughout and one of the key drivers is as I touched on, has probably been the revised demand and pricing coming through in the model. And the biggest negative to what's happened with the DFS has been the movement in currency, particularly the US dollar and Australian rates. The total capital requirement of $482 million approximately, that includes all pre-production costs, startup working capital, environmental bond, and corporate costs right through to commercial production. So, we're very confident that we've included everything that is needed to be taken account of in those numbers and sit very much ready now to get on with it as soon as we can with funding in place.
Andrew Musgrave
And you mentioned earlier the dual revenue streams. How important is that second revenue stream to the project's economics?
Andrew King
Look, Andrew, I think it's probably fair to say that having dual two revenue streams is actually fundamental to the project. It gives the Goschen project real resilience and market strength going forward. As I mentioned earlier, you know, before we take any credit for the heavy mineral concentrate, the total operating cost in relation to rare earths is about $21 US per kilogram of rare earth oxide. Once we put that credit back in as a revenue, that reduces that rare earth oxide cost to about $7 per kilogram. So, with that second revenue streaming covering a substantial part of our operating costs, it completely reduces our exposure to the volatility and rare earth prices and gives real strength to the financing case for lenders driven by that diversified cash flow rather than just relying on a single product.
Andrew Musgrave
You mentioned the non-binding term sheet with Mitsui for up to 50% of Goschen's heavy mineral concentrate production following your rare earth offtake with Iluka. How does this partnership with Mitsui complete your commercial and funding puzzle for the project?
Andrew King
I think it very much underpins that story about having a second product and the route to market for that. The pricing for it is market-linked and with a strong Japanese counterparty. Again, it just very much reinforces the position we have in the marketplace and the comfort that we can give to investors and financiers about our route to market and how secure it is.
Andrew Musgrave
You've now secured key approvals with both the federal and Victorian governments, and major work packages have been tendered or substantially advanced. What does being construction ready actually mean for VHM at this stage?
Andrew King
Look, being construction ready means exactly as you've described, we have all key federal and Victorian approvals, and we're ready to go in terms of construction. We have land access for the project and will own all the land that we need to both construct and mine through the mining license. Every major work package has been tendered and evaluated. We have preferred contractors identified, long lead items of equipment are known, and we have an integrated delivery schedule for the project. So, again, once financing is in place, we are ready to mobilize quickly. We don't require any more feasibility studies or we're not waiting for any more permits, it means we can get underway straight away.
Andrew Musgrave
You've also received a non-binding letter of support from Export Finance Australia for up to AUD75 million and a letter of interest from the US Export Import Bank for up to US $200 million. How do these fit into the overall funding plan and what's left to reach financial close?
Andrew King
If you look around the world at the moment, there is not a rare earth project anywhere in the Western world that is in development without some sort of government support. As we touched on, our agreement with Iluka is very important to that. We will be providing critical rare earth feedstock to the Iluka Eneabba Rare Earth Oxide Refinery. That will be the first oxide refinery in Australia and is an asset of national importance. And we will be supplying into that. So, our discussions with government are very well advanced on that basis, and uh we will take that forward as the key next step in terms of delivering FID.
Andrew Musgrave
Finally, Andrew, as we close out 2026 and look to 2027, what are the key priorities over the next six to 12 months for VHM?
Andrew King
Well, as we touched on, I think first key priority is completing the financing and reaching FID. In parallel with that, as we touched on earlier, we will be taking our extensive non-binding agreement with Mitsui to a binding agreement. That's being done in parallel. And in those discussions, we're talking with Mitsui about expanding that to 100% of that HMC product together with the working capital support that they are discussing. We are building an owner's team and getting operationally ready to commence construction and move then into production. So fully permitted, technically de-risked. The next 12 months is finalizing the financing and the full financing package and getting on with construction to then be in a position to deliver key inputs, particularly to Iluka and the Eneabba project, which is due to come on stream at the back end of next year.
Andrew Musgrave
Okay, Andrew, well, it's been great to have you on the podcast today. So, thanks for your time, and we look forward to following the progress at Goschen over the coming 12 months.
Andrew King
Andrew, thank you, and thank you to your listeners for your time.
Andrew Musgrave
That concludes this episode of ASX Briefs. Don't forget to subscribe, and we look forward to catching you on our next episode.